Budget at Completion Calculator
Budget at completion (BAC)
600.00
Budget at Completion and Earned Value Calculator
Components summed
3
Worked out from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), Control Costs - earned value analysis, forecasting and the to-complete performance index and 2 other sources.
This is a summation of authorised budget only. It carries no statement about baseline authorisation, change control, contingency or management reserve, and no earned-value conclusion.
Earned value measures what a schedule and a cost account already say. It is only as good as the percent-complete figures fed into it, and a single-period index is a weak forecast on its own.
How this is worked out
2 steps
- Budget at completion is the sum of the approved budget components.
- BAC = 100 + 200 + 300 = 600.